Specialist triumphant in late-payments disagreement

Specialist triumphant in late-payments disagreement

1 minute, 50 seconds Read

An East Grinstead professional has effectively reversed a legal choice that discovered it was incorrect to end its agreement with a realestate association over duplicated late payments.

The disagreement occurred from a JCT agreement inbetween Providence Building Services Limited and Hexagon Housing Association Limited (Hexagon) for the buildingandconstruction of structures in Purley, valued at £7.2m.

The secret concern was whether Providence might end its agreement after Hexagon stoppedworking to pay an billing on time, even however Hexagon had paid up within 28 days of getting a previous default notification.

Mark London, partner at Devonshires, which represented Hexagon, stated: “The Court of Appeal’s judgment hasactually presented a considerable threat to companies allover who, in the occasion of a defined default, will face the proverbial sword of Damocles for the rest of the agreement.

“Contrary to the method in which the building market has ran the JCT termination arrangements because the present phrasing was presented in the 2005 JCT suite, companies will now be subject to a ‘two strikes and you’re out’ routine.

“If they are late making a single payment, even by one day, the specialist will undoubtedly serve a default notification.  If it takesplace onceagain then the specialist might end – even if the previous late payment is withoutdelay treated.  This will be a possibly effective tool in the armoury of a specialist that wants to exit an unprofitable task.”

In November 2022, Hexagon stoppedworking to pay an billing of £264,000 by the due date.

Under the agreement, if Hexagon did not make the payment within 21 days, Providence had the right to suspend its work.

However, if the payment was still not made after a evenmore 7 days, Providence might end the agreement.

Providence provided a official notification of default, which alerted Hexagon that it was in breach of its payment commitments. Hexagon made the payment within 28 days, which avoided Providence from instantly ending the agreement at that time.

However, in April 2023, Hexagon onceagain stoppedworking to make another payment of £366,000 by the due date.

This time, Providence ended the agreement, pointingout Hexagon’s duplicated failure to pay on time.

Providence argued that the duplicated late payment was adequate premises for termination, even however it had not ended the agreement after t

Read More.